Project Description

The Hooper Corporation project included the demolition of six buildings, reworking of the large truck traffic flow and vehicle parking, and additions to the electric power division maintenance shop and a new 7,600 square foot pipe fabrication shop. The 25,500 square foot maintenance shop includes a 10-ton bridge crane, two 8-ton rotary lifts, and two 38-ton rotary lifts. The pits dug for the lifts proved a challenge for the field crew due to the high water level in this area of Madison.
Vogel Bros. led the team through a successful City of Madison approval process in just two months, and then begin demolition and construction for this fast-track project. The project includes three Butler metal buildings for the additions which enabled the team to meet the owner’s aggressive schedule.